March 18, 2020

This warehouse facility had PSI remove fifteen (15) + sections of the old concrete and replace with new concrete leading up to one (1) extra-large dock door. The concrete was formed-up in large sections, 4” of gravel, rebar mat and then 12” reinforced,  high strength concrete was poured. The concrete has a broom finish. PSI added a concrete terrace from the upper loading dock area to the lower loading dock area. A heavy-duty metal railing was installed along the edge of the terrace and two (2) Bollards were installed at each corner of the load dock door. The final step of the project included installing flexible joint compound to all expansion joints.